Project
Chickadee
New Brunswick, Canada
Challenge / Roadblock
Build 182 kilometers of fiber backbone with just 3 weeks lead-time, using out-of-province resources exclusively because all local resources are provisioned for post-Hurricane Fiona clean-up and repairs.
182km in New Brunswick, Canada
3 week lead-time. 47km/Week Peak Build Rate.
Watch the director's cut
Copied!
SOLUTION
Vytal quickly mobilized 6 crews from different provinces to create a 32-person onsite team, with a 6 person back office support team operating across 3 timezones, working 17 hours a day to get the job done.
Stats / Interesting Facts
- 3 week lead-time
- Peak build rate: 47KM/week
- 13 week build
- 6 crews/32 Onsite team
- 6 backoffice support
- Operating across 3 timezones
- 182Km build
End-to-End Fiber Network
Design and Construction.