Project
Cinnamon Teal

Manitoba, Canada

Project Objective

To upgrade and expand the Brandon Airport’s fiber infrastructure, link the city’s RCMP emergency services and improve local networks and commercial broadband access.

Challenge / Roadblock

Adapt to a constantly evolving project that grew in scope and that involved more interested parties as time went on, while respecting the timeline and budget of the original client.

17km+ FTTX fiber build in Brandon, Manitoba

15 weeks. Completed ahead of schedule and on budget.

SOLUTION

Lean on our turnkey approach and our nimbleness to adapt to the project’s evolution, and strategically call upon joint build partners to help share costs, expand their networks, and provide value-added outcomes to the Brandon municipality.

Stats / Interesting Facts

  • Connections between the Brandon Airport, Brandon emergency services (RCMP), Brandon Sportsplex and multiple booster stations
  • Strategic collaboration (joint build) with Westman Communications, Telus and BellMTS
  • 17000+ meters of infrastructure built

Partners

Collaborated closely with Zayo, local authorities, and technology providers to ensure a cohesive and efficient design process.

End-to-End Fiber Network

Design and Construction.